12/14/2010

This is the service/office building. It is in current demo mode. Originally it was suppose to be just remolded and a new roof but they have discovered that the building is in worse shape than they thought so at the moment we are awaitng the word to find out what will happen to the building......no matter what this adds on to the length of the project so we will be here a little longer.....
 This is the new kitchen/dinning room extention. It is suppose to be completed in middle Jan and they sill move in and be fully functioning in Feb for the upcoming zone visit.
 Here is the inside of the extention...what you are looking at is what will be the dinning room area.
 And this is the shops building....still has a lot to be finished before we can completely turn it over to the branch because construction is using a lot of it for storage and a carpentry shop.